Intricate Scaffold design for St Michael le Belfrey
The scaffolding is nearly complete!
Simpson started on 5 August 2024, preparing the site of the church building. After some careful redesign, which uses a ladder system to protect the floor and the vaults underneath the surface, ADS Scaffolding has nearly completed the erection of the scaffold inside the building and continues to build the scaffold externally.
At the first stage and higher stage, certain window panes have been removed by Barley Studio to ‘tie’ the scaffolding through the window apertures.
This means that no scaffold is attached directly to the building which is important as it ensures the Grade I listed fabric is better protected.
The result is almost architectural in itself.
Please pray for: ADS that they can complete the scaffolding without any delays or difficulties and Simpson as they look ahead and turn their attention to the masonry repairs and cleaning off the paint.